Agenda

  1. Continue discussion on Sustainability Alternatives
  2. Review project adjacencies & related efficiencies: Media Center, Dining & Food Service

Documents and video

What came out of it

  1. $2.9 million off the estimated cost — 2,700 sq ft trimmed

    The Building Committee approved: Space Reduction Efficiencies Related to MEEP & Curtis-Tufts Therapeutic Day Program. The proposed building is now 585,816 sq ft, with an estimated total project cost of $765.7 million.

    Meeting slides (project cost reduction summary) (PDF)