Medford High School
Building Project
PROJECT INTRODUCTION
Welcome to the Medford High School Building Project!
This website is your resource for information about the project, the partnership with the Massachusetts School Building Authority (MSBA), the schedule, process and upcoming steps.
The project team are currently conducting the Feasibility Study which will include the status of the current conditions, and development and evaluation of potential alternative solutions, and finally helping the district come up with a final, preferred option. They will then continue through the Schematic Design Phase to determine the most educationally appropriate and fiscally responsible option for the school.
Medford High School is the largest public high school serving 9th grade – 12th grade enrollment in the City of Medford. As a result of the collaborative analysis with the Massachusetts School Building Authority of enrollment projections and space capacity needs, the design alternatives will be evaluated as part of the feasibility study based on an enrollment of 1,395 students.
The entire Feasibility Study process is estimated to take 18-24 months.
PROJECT UPDATE
Module 3 – Feasibility Study
The project is moving forward with PSR (Preferred Schematic Report). On February 25, 2026 the project team submitted the PDP submission which included detailed information about the existing conditions of the school, a preliminary educational plan, preliminary space program, and 29 preliminary options. Those 29 options were then reviewed by the MCHSBC and on March 23 the committee reduced the number of options down to 6. On June 10 they then reduced it down to the preferred option – Option C.2.2A. Next step in the process is submitting the PSR report on June 25, 2026 to the MSBA, and this preferred option will then be further developed through to Schematic Design process.
Milestone Activities
Module 1: Eligibility Period
Module 2: Forming the Team
MAR 2025 – MAY 2025
OPM Selection
JUL 2025 – NOV 2025
Designer Selection
Module 3: Feasibility Study
OCT 2025 – FEB 2026 – Completed
Preliminary Design Proposal (PDP)
FEB 2026 – JUN 2026 – Submit 6/25/26
Preferred Schematic Report (PSR)
AUG 2026 (Estimated)
MSBA Board of Directors – PSR Approval
Module 4: Schematic Design
AUG 2026 – APR 2027 (Estimated)
Schematic Design Development
MSBA Board of Directors Approval
Execute Project Scope and Budget Agreement
Module 5: Funding the Project
MAR – APR 2027 (Estimated)
City of Medford Vote for Approval of Project
Execute Project Funding Agreement with the MSBA
Module 6: Detailed Design
MAR – DEC 2027 (Estimated)
Design Development Drawings and Submission
60% Construction Document Drawings and Submission
90% Construction Document Drawings and Submission
100% Construction Document Drawings and Submission
Module 7: Construction
JUN 2028 – JUN 2030 (Estimated)
Construction
Module 8: Completing the Project
JUN 2030 – DEC 2031 (Estimated)
Closeout of the Project with the MSBA
Medford High School Building Committee Meeting
July 22 at Medford High School Library
Medford High School Building Committee Meeting
August 25 at Medford High School Library
Medford High School Building Committee Meeting
September 22 at Medford High School Library
PREVIOUS MEETINGS
Medford High School Building Committee Meeting
June 18 at Bistro 489
Medford School Committee Meeting - Project Update
June 15 at Medford City Hall
Medford High School Building Committee Meeting
June 10 at Medford High School Library
Community Forum #5
June 3, 2026 at Medford High School Library
All other previous meetings are listed in the Meetings/Events tab. Each calendar event contains links to the agenda and presentation shown during the meeting.
SHORTCUTS
MSBA WEBSITE
Click here for more information about funding and the MSBA process
GLOSSARY OF TERMS
Click here for a guide to clarify common terms used in the building process for public projects.
FAQ'S
Click here for a list of frequently asked questions on the project.
