Medford High School
Building Project

PROJECT INTRODUCTION

Welcome to the Medford High School Building Project!

This website is your resource for information about the project, the partnership with the Massachusetts School Building Authority (MSBA), the schedule, process and upcoming steps.

The project team are currently conducting the Feasibility Study which will include the status of the current conditions, and development and evaluation of potential alternative solutions, and finally helping the district come up with a final, preferred option. They will then continue through the Schematic Design Phase to determine the most educationally appropriate and fiscally responsible option for the school.

Medford High School is the largest public high school serving 9th grade – 12th grade enrollment in the City of Medford. As a result of the collaborative analysis with the Massachusetts School Building Authority of enrollment projections and space capacity needs, the design alternatives will be evaluated as part of the feasibility study based on an enrollment of 1,395 students.

The entire Feasibility Study process is estimated to take 18-24 months.

PROJECT UPDATE

Module 3 – Feasibility Study

The project is moving forward with PSR (Preferred Schematic Report). On February 25, 2026 the project team submitted the PDP submission which included detailed information about the existing conditions of the school, a preliminary educational plan, preliminary space program, and 29 preliminary options. Those 29 options were then reviewed by the MCHSBC and on March 23 the committee reduced the number of options down to 6.  On June 10 they then reduced it down to the preferred option – Option C.2.2A. Next step in the process is submitting the PSR report on June 25, 2026 to the MSBA, and this preferred option will then be further developed through to Schematic Design process.

Milestone Activities

APR 2023 - FEB 2025
APR 2023 - FEB 2025

Module 1: Eligibility Period

MAR 2025 - NOV 2025
MAR 2025 - NOV 2025

Module 2: Forming the Team

MAR 2025 – MAY 2025
OPM Selection

JUL 2025 – NOV 2025
Designer Selection

OCT 2025 - AUG 2026
OCT 2025 - AUG 2026

Module 3: Feasibility Study

OCT 2025 – FEB 2026 – Completed
Preliminary Design Proposal (PDP)

FEB 2026 – JUN 2026 – Submit 6/25/26
Preferred Schematic Report (PSR)

AUG 2026 (Estimated)
MSBA Board of Directors – PSR Approval

AUG 2026 - APR 2027
AUG 2026 - APR 2027

Module 4: Schematic Design

AUG 2026 – APR 2027 (Estimated)
Schematic Design Development

MSBA Board of Directors Approval

Execute Project Scope and Budget Agreement

MAR - APR 2027
MAR - APR 2027

Module 5: Funding the Project

MAR – APR 2027 (Estimated)
City of Medford Vote for Approval of Project

Execute Project Funding Agreement with the MSBA

MAR - DEC 2027
MAR - DEC 2027

Module 6: Detailed Design

MAR – DEC 2027 (Estimated)
Design Development Drawings and Submission

60% Construction Document Drawings and Submission

90% Construction Document Drawings and Submission

100% Construction Document Drawings and Submission

JUN 2028 - JUN 2030
JUN 2028 - JUN 2030

Module 7: Construction

JUN 2028 – JUN 2030 (Estimated)
Construction

JUN 2030 - DEC 2031
JUN 2030 - DEC 2031

Module 8: Completing the Project

JUN 2030 – DEC 2031 (Estimated)
Closeout of the Project with the MSBA

Updated MSBA Meeting Dates

Medford High School Building Committee Meeting

July 22 at Medford High School Library

Medford High School Building Committee Meeting

August 25 at Medford High School Library

Medford High School Building Committee Meeting

September 22 at Medford High School Library

PREVIOUS MEETINGS

Medford High School Building Committee Meeting

June 10 at Medford High School Library

Community Forum #5

June 3, 2026 at Medford High School Library

All other previous meetings are listed in the Meetings/Events tab. Each calendar event contains links to the agenda and presentation shown during the meeting.

SHORTCUTS

MSBA WEBSITE

Click here for more information about funding and the MSBA process

GLOSSARY OF TERMS

Click here for a guide to clarify common terms used in the building process for public projects.

FAQ'S

Click here for a list of frequently asked questions on the project.