What has happened

The whole story, newest first. Every item links to the meeting or document behind it.

The eight phases

The MSBA process runs in modules. Dates after today are estimates from the project schedule.

  1. Eligibility (complete)

    April 2023 – February 2025

    Medford asked the MSBA for help and proved the need.

  2. Forming the team (complete)

    March – November 2025

    Hired the owner's project manager (LeftField) and the designer (SMMA).

  3. Feasibility study (complete)

    October 2025 – August 2026

    Studied the existing building, wrote the educational plan, compared 29 options, chose one.

  4. Schematic design Now

    August 2026 – April 2027 (estimated)

    Develop the chosen option in detail, settle the scope and budget with the MSBA.

  5. Funding the project

    March – April 2027 (estimated)

    Medford voters decide on a debt exclusion; the City and the MSBA sign the funding agreement.

  6. Detailed design

    March – December 2027 (estimated)

    Construction drawings, from design development to 100% construction documents.

  7. Construction

    June 2028 – June 2030 (estimated)

    Build it.

  8. Completing the project

    June 2030 – December 2031 (estimated)

    Move in, finish the site, close out with the MSBA.

Milestones and decisions

  1. April 2027 · planned

    MSBA Board approval of scope and budget (planned)

  2. April 2027 · planned

    Medford votes on a debt exclusion (planned, spring 2027)

    Voters decide whether to fund the City's share; the City Council authorizes borrowing; the City and MSBA sign the Project Funding Agreement.

  3. February 2027 · planned

    Schematic Design submission to the MSBA (planned)

  4. Oct 6, 2026

    $48.9 million off the estimated cost — 2,409 sq ft trimmed

    The Building Committee approved: Final Space Reduction Efficiencies. The proposed building is now 567,877 sq ft, with an estimated total project cost of $699.9 million.

    Meeting slides (project cost reduction summary) (PDF)

  5. Sep 22, 2026

    $16.9 million off the estimated cost — 15,530 sq ft trimmed

    The Building Committee approved: Space Reduction Efficiencies Related to Core Academic, Medford Academy, Special Education, and CTE Spaces. The proposed building is now 570,286 sq ft, with an estimated total project cost of $748.8 million.

    Meeting slides (project cost reduction summary) (PDF)

  6. Sep 10, 2026

    $2.9 million off the estimated cost — 2,700 sq ft trimmed

    The Building Committee approved: Space Reduction Efficiencies Related to MEEP & Curtis-Tufts Therapeutic Day Program. The proposed building is now 585,816 sq ft, with an estimated total project cost of $765.7 million.

    Meeting slides (project cost reduction summary) (PDF)

  7. Aug 26, 2026

    MSBA accepts the project into Schematic Design

    The MSBA Board of Directors approved the Preferred Schematic Report, moving the project into Module 4.

    Acceptance letter (PDF)

  8. Aug 25, 2026

    $25.8 million off the estimated cost — 20,276 sq ft trimmed

    The Building Committee approved: Space Reduction Efficiencies Related to Medford Community Media, Community Rental Partner Storage, Community Meeting Space, Health & PE, Auditorium Size, and Art & Music Spaces. The proposed building is now 588,516 sq ft, with an estimated total project cost of $768.6 million.

    Meeting slides (reductions begin on page 12, summary on slide 23) (PDF)

  9. Jul 29, 2026

    MSBA comments on the PSR; district responds

    The MSBA sent two sets of comments on the Preferred Schematic Report (general comments and a review of the space summary). The district, LeftField and SMMA returned their responses on August 12, and on August 19 the MSBA confirmed the project would go to its Board on August 26.

  10. Jun 25, 2026

    Preferred Schematic Report (PSR) submitted to the MSBA

    Proposed building of 608,792 gross sq ft; estimated total project cost $794.4 million.

    PSR: preferred solution (PDF)

  11. Jun 18, 2026

    10,020 sq ft trimmed from the project (saving to be confirmed)

    The Building Committee approved: Reduction to CTE Toilet Rooms, Changing Rooms, Storage, & Office Spaces.

    Space efficiencies approved (slide 5) (PDF)

  12. Jun 10, 2026

    Preferred option chosen: C.2.2A

    An addition and renovation on the existing site: a new six-story academic building replacing the arts, academic and vocational wings, with the pool and gyms kept and renovated. Estimated at the time: $813 million total, of which Medford's share would be roughly $591 million before the MSBA reimbursement rate is final.

    Option C.2.2A summary (PDF)

  13. May 20, 2026

    MSBA comments on the PDP, and the district's response

    MSBA comments (PDF)

  14. Apr 27, 2026

    24,390 sq ft trimmed from the project (saving to be confirmed)

    The Building Committee approved: Space Reductions Proposed by MPS Educational Leadership Team.

    Meeting minutes (reductions begin on page 6) (PDF)

  15. Mar 23, 2026

    29 options narrowed to 6

    The six options (PDF)

  16. Feb 25, 2026

    Preliminary Design Program (PDP) submitted to the MSBA

    Existing conditions, the educational plan, a space summary of 639,879 sq ft, and 29 preliminary design options.

    PDP, part 1 of 6 (PDF)

  17. Jan 7, 2026

    Community Forum #1

  18. Dec 16, 2025

    Four advisory teams start meeting

    Interior & Exterior Design; Sustainability & Building Systems; Educational Planning & Equity; Site, Safety & Security. Each met three times through March 2026 and handed the committee written recommendations.

  19. Dec 9, 2025

    Educational visioning workshops

    Three day-long sessions with educators (December 9 and 17) that shaped the educational plan.

    Visioning report (PDF)

  20. November 2025

    SMMA selected as designer

    Chosen through the MSBA's Designer Selection Panel process (panel meetings September 23 and October 7, 2025); the contract was on the Building Committee's November 24 agenda.

    SMMA's proposal (PDF)

  21. Jun 2, 2025

    LeftField selected as owner's project manager

    The MSBA's OPM review panel approved the selection on June 2, 2025.

    LeftField's proposal (PDF)

  22. May 12, 2025

    First Building Committee meeting

  23. Feb 26, 2025

    MSBA Board votes Medford into the Feasibility Study

    A unanimous vote. The City signed the Feasibility Study Agreement that set the study in motion.

    Feasibility Study Agreement (PDF)

  24. July 2024

    Enrollment study submitted

    The MSBA later certified a design enrollment of 1,395 students in grades 9–12.

    Enrollment study (PDF)

  25. Apr 30, 2024

    Initial Compliance Certification signed

    Certification (PDF)

  26. Apr 13, 2023

    Statement of Interest submitted to the MSBA

    The first step: Medford told the Massachusetts School Building Authority why the 1970 high school no longer serves its students.

    Statement of Interest (PDF)

How the building size has changed

The proposed building is 567,877 sq ft as of Tuesday, October 6, 2026, with an estimated total project cost of $699.9 million. See every change to the size and cost, with its source.