159 results for “cost”.

  1. Decision

    $25.8 million off the estimated cost — 20,276 sq ft trimmed

    Tuesday, August 25, 2026

    … lding is now 588,516 sq ft, with an estimated total project cost of $768.6 million.

  2. Decision

    $2.9 million off the estimated cost — 2,700 sq ft trimmed

    Thursday, September 10, 2026

    … lding is now 585,816 sq ft, with an estimated total project cost of $765.7 million.

  3. Decision

    $16.9 million off the estimated cost — 15,530 sq ft trimmed

    Tuesday, September 22, 2026

    … lding is now 570,286 sq ft, with an estimated total project cost of $748.8 million.

  4. Decision

    $48.9 million off the estimated cost — 2,409 sq ft trimmed

    Tuesday, October 6, 2026

    … lding is now 567,877 sq ft, with an estimated total project cost of $699.9 million.

  5. Question

    How much will the project cost, and how much will Medford pay?

    Project Funding and Cost

    … Schematic Design Phase. The MSBA reimbursement for eligible costs will be voted on at the April 2027 MSBA Board of Directors Meeting. As of the October 6, 2026 meeting, the total project cost is estimated at $699,862,410 …

  6. Question

    Why does Medford's project cost more than recent high schools in Waltham and Brockton?

    Project Funding and Cost

    The MSBA has seen dramatic cost increases in school construction in recent years due to market factors and material costs. When comparing our project to neighboring communities, the project start and completion timeline …

  7. Question

    Why do different School Districts get Different Reimbursement Rates for Eligible Costs?

    Project Funding and Cost

    … on/Re-use of Existing Facilities (up to 5 percentage points)

  8. Document · PDF

    SBC Minutes 4/27/26 (PDF)

    Monday, April 27, 2026

    Offered by Jenny Graham and Dr. Suzanne Galusi: Be it resolved that the next round of cost estimating will provide cost estimates breakdown as follows: ■ Parking: a) Base estimate will include surface grade parking

    Minutes for Building Committee Meeting, Apr 27, 2026

  9. Document · PDF

    SBC Agenda 4/27/26 (PDF)

    Monday, April 27, 2026

    Offered by Jenny Graham and Dr. Suzanne Galusi: Be it resolved that the next round of cost estimating will provide cost estimates breakdown as follows: 1. Parking: a) Base estimate will include surface grade parking

    Agenda for Building Committee Meeting, Apr 27, 2026

  10. Document · PDF

    SBC Presentation 6/1/26 (PDF)

    Monday, June 1, 2026

    Meeting Minutes ➢ Project Updates & Follow-ups ➢ Medford Update on Capital Projects and Preliminary Estimate of Project Costs Impact ➢ Review PSR Cost Estimate for C2.2A & C3.4A ➢ Project Timeline June 2026 – June 2027 ➢ Updated Evaluation Criteria Matrix

    Presentation slides for Building Committee Meeting, Jun 1, 2026

  11. Document · PDF

    SBC Presentation 3/23/26 (PDF)

    Monday, March 23, 2026

    Operations (4%) Trailheads & Connection to the Fells (4%) Community Gathering Facilities (3%) Construction Timeline (2%) Keeping Construction Costs Low 416 Votes Community Health Center, Counseling/ Youth Center Pest control during demolitions Healthy Indoor building, Indoor

    Presentation slides for Building Committee Meeting, Mar 23, 2026

  12. Document · PDF

    Sustainability & MEP Systems Avisory Presentation 9/23/26 (PDF)

    Wednesday, September 23, 2026

    Agenda ➢ Sustainability Givens Overview ➢ Net Zero Energy & Minimizing Cost of Ownership • Preliminary Life Cycle Cost Analysis (LCCA) Information ➢ Preliminary Solar PV Assessment ➢ Red List Free Materials ➢ Embodied Carbon & Mass Timber ➢ Water Efficiency & Stewardship ➢ Next Steps

    Presentation slides for Sustainability & MEP Systems Advisory Meeting, Sep 23, 2026

  13. Document · PDF

    2026.09.23 Sustainability & Systems Advisory Team Meeting #6 (PDF)

    Wednesday, September 23, 2026

    Action Discussion 06.01 Record Meeting #6 Agenda Welcome & introductions • Sustainability Givens Overview • Net Zero Energy & Minimizing Cost of Ownership Preliminary Life Cycle Cost Analysis (LCCA) Information ○ • Preliminary Solar PV Assessment • Red List Free Materials • Embodied

    Minutes for Sustainability & MEP Systems Advisory Meeting, Sep 23, 2026

  14. Document · PDF

    Community Forum #2, March 5, 2026 — community workshop follow-up input (March 16, 2026) (PDF)

    Thursday, March 5, 2026

    Code Upgrade Option Alt A.1 Cost: ~$437M New Building Footprint Existing Building Footprint Summary: • Base Repair at the existing Medford High School facility • Estimated total project cost

    Document for Community Forum #2, Mar 5, 2026

  15. Document · PDF

    SBC Presentation 2/11/26 (PDF)

    Wednesday, February 11, 2026

    Amendment #1 • Summary of Reactions to Alternatives • PDP Submission Status - due 2/25 • Educational Plan • Space Summary Review • Cost Information for January 14, 2026 Alternatives • Introduction of Evaluation Criteria • Review of Cost Information for January

    Presentation slides for Building Committee Meeting, Feb 11, 2026

  16. Document · PDF

    Building Committee Meeting, February 11, 2026 — pDP Comparative Cost Analysis (PDF)

    Wednesday, February 11, 2026

    Cost Estimates The following slides are an excerpt from the February 11, 2026 Meeting of the Medford Comprehensive High School Building Committee Meeting. Visit https://medfordhsproject.com/event/medford-high-school-building-co mmittee-meeting-february-11-2026/for full meeting

    Document for Building Committee Meeting, Feb 11, 2026

  17. Document · PDF

    Community Forum #5 6/3/26 (PDF)

    Wednesday, June 3, 2026

    High School Community Forum #5 06/03/2026 06/08/2026 rev1 – updated with Winthrop St. Perspectives and Estimated District Share Costs

    Presentation slides for Community Forum #5, Jun 3, 2026

  18. Document · PDF

    Sustainability & MEP Systems Advisory Meeting, March 10, 2026 — presentation slides (PDF)

    Tuesday, March 10, 2026

    Meeting #3 Agenda • Welcome & Introductions • Advisory Team Recommendation Development • Life Cycle Cost Analysis (LCCA) Overview • Next Steps

    Presentation slides for Sustainability & MEP Systems Advisory Meeting, Mar 10, 2026

  19. Document · PDF

    SBC Presentation 2/23/26 (PDF)

    Monday, February 23, 2026

    Agenda ➢ Roll call ➢ Approval of Meeting Minutes • February 11 Full Committee Meeting ➢ Cost Estimate Updates ➢ Vote to approve submission of Preliminary Design Program Report ➢ Evaluation Criteria Review ➢ Adjournment

    Presentation slides for Building Committee Meeting, Feb 23, 2026

  20. Document · PDF

    Appendices (PDF)

    Thursday, June 25, 2026

    Meetings D. LEEDv5 Scorecard E. MHS Educational Plan – (clean version) F. MHS Educational Plan – (track changes) G. Cost Information i. PSR Cost Estimate (AM Fogarty) ii. Comparative Cost Analysis iii. Preliminary Design Pricing Table