122 results for “parking”.

  1. Question

    How many parking spaces will there be?

    What changes can be expected on the campus/site?

    The site design assumed about 450 parking spaces. After additional coordination with District stakeholders, the current parking count target is 477. Details on the breakdown of the 477 spaces are available here .

  2. Document · PDF

    Community Forum #4 5/11/26 (PDF)

    Monday, May 11, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Community Forum #4, May 11, 2026

  3. Document · PDF

    Updated PSR Design Options (Shared on 4/27/26) (PDF)

    Monday, April 27, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Document for Building Committee Meeting, Apr 27, 2026

  4. Document · PDF

    SBC Presentation 4/27/26 (PDF)

    Monday, April 27, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Building Committee Meeting, Apr 27, 2026

  5. Document · PDF

    Abutters Meeting #2 5/13/26 (PDF)

    Wednesday, May 13, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Abutters Meeting #2, May 13, 2026

  6. Document · PDF

    SBC Presentation 5/20/26 (PDF)

    Wednesday, May 20, 2026

    Restriction Alternative) New Building Footprint Existing Building Footprint 9 Summary: • Addition/renovation (On the Existing Footprint, on the Parking Lot to the west and a portion of Edgerly Field to the north) which proposes

    Presentation slides for Building Committee Meeting, May 20, 2026

  7. Document · PDF

    Parking Memo & Plan (PDF)

    Tuesday, August 25, 2026

    Lord Project Number: 25100 From: Laura Swan Date: 8/25/2026 Project Name: Medford High School RE: Parking Program-DRAFT Distribution: This memorandum is intended to describe our best understanding of the existing parking utilized

    Document for Building Committee Meeting, Aug 25, 2026

  8. Document · PDF

    Final Evaluation of Alternatives (PDF)

    Thursday, June 25, 2026

    Building Location Existing Footprint Existing Footprint Existing Footprint & Fields Existing Footprint & Fields Existing Footprint & Fields Parking Lot & Existing Footprint Parking Lot & Existing Footprint Modulars Required

  9. Document · PDF

    Evaluation of Existing Conditions (PDF)

    Thursday, June 25, 2026

    other site improvements vary significantly between the six PSR Alternatives; A.1, B.1.2, C2.2, C.3.4, D.1.1, and D.2.1. Parking options being considered include surface parking, construction of a 4-story parking garage, or field/stadium over below

  10. Document · PDF

    SBC Presentation 2/11/26 (PDF)

    Wednesday, February 11, 2026

    subcontractor expenses (not CM expenses). For this PDP level estimate these categories are: Renovation, Addition/New Construction, Sitework, Parking, Pool Scope, Hazmat Removal and Demolition (See rows 1-10) Construction Cost The cost of construction which

    Presentation slides for Building Committee Meeting, Feb 11, 2026

  11. Document · PDF

    Building Committee Meeting, February 11, 2026 — pDP Comparative Cost Analysis (PDF)

    Wednesday, February 11, 2026

    subcontractor expenses (not CM expenses). For this PDP level estimate these categories are: Renovation, Addition/New, Sitework, Parking, Pool Scope, Hazmat Removal and Demolition (See rows 1-11) Construction Cost The cost of construction which Includes

    Document for Building Committee Meeting, Feb 11, 2026

  12. Document · PDF

    Building Committee Meeting, March 23, 2026 — six Design Options Chosen (PDF)

    Monday, March 23, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Document for Building Committee Meeting, Mar 23, 2026; Document for Community Forum #3, Apr 15, 2026

  13. Document · PDF

    Community Forum #3 4/15/26 (PDF)

    Wednesday, April 15, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Community Forum #3, Apr 15, 2026

  14. Document · PDF

    Final 6 PSR Design Options Presentation (PDF)

    Monday, June 1, 2026

    Educational Program • Existing 4 Stories to remain • Estimated duration of 60 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Maintains existing field inventory - Edgerly fields

    Meeting notes for Building Committee Meeting, Jun 1, 2026

  15. Document · PDF

    Community Forum #5 6/3/26 (PDF)

    Wednesday, June 3, 2026

    Educational Program • Existing 4 Stories to remain • Estimated duration of 60 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Maintains existing field inventory - Edgerly fields

    Presentation slides for Community Forum #5, Jun 3, 2026

  16. Document · PDF

    SBC Presentation 3/23/26 (PDF)

    Monday, March 23, 2026

    located so all students will access these spaces. So students do not feel singled out or 'special'. " • Parking congestion • Traffic flow • Bathroom privacy/safety • Pick-up/drop-off logistics. "Make a path for cars that goes completely

    Presentation slides for Building Committee Meeting, Mar 23, 2026

  17. Document · PDF

    SBC Presentation 6/10/26 (PDF)

    Wednesday, June 10, 2026

    folding into the high school project." D1.1 – ( 22) VOTES "D.1.1 NP — choosing this because I like the parking in the middle, making fields and building equally accessible, a new pool and gym ensure

    Presentation slides for Building Committee Meeting, Jun 10, 2026

  18. Document · PDF

    2026 10 01 Sustanability & Systems AT Meeting 07 notes (PDF)

    Thursday, October 1, 2026

    Officer Sarah Michelman, Medford Resident, Sustainable Design Consultant at The Green Engineer Nicole Morell, SBC Member Jessica Parks, Medford Resident, MIT Energy Efficiency Project Manager Brenda Pike, City of Medford Climate Policy Planner Luke Preisner

    Minutes for Sustainability & MEP Systems Advisory Meeting, Oct 1, 2026

  19. Document · PDF

    Site, Safety & Security Advisory Meeting, 2026-10-01: Presentation slides (PDF)

    Thursday, October 1, 2026

    Meeting #4 Agenda • Welcome & Introductions • Advisory Team Recommendation Development ❑ Parking Program ❑ Updated Site Layout ❑ Edgerly Track & Field ❑ Pedestrian Experience: ECC Breezeway ❑ Call for Assistance/ AED • Next Steps

    Presentation slides for Site, Safety & Security Advisory Meeting, Oct 1, 2026

  20. Document · PDF

    Evaluation Criteria Matrix (PDF)

    Thursday, March 19, 2026

    Addition Retain and Renovate Gym, Pool, and Wing E while constructing a New Addition on Parking Lot Retain and Renovate Gym, Pool and Wing E while constructing a New Addition in the center

    Document for Building Committee Meeting, Mar 17, 2026