124 results for “parking”.

  1. Question

    How many parking spaces will there be?

    What changes can be expected on the campus/site?

    The site design assumed about 450 parking spaces. After additional coordination with District stakeholders, the current parking count target is 477. Details on the breakdown of the 477 spaces are available here .

  2. Document · PDF

    Community Forum #4 5/11/26 (PDF)

    Monday, May 11, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Community Forum #4, May 11, 2026

  3. Document · PDF

    Abutters Meeting #2 5/13/26 (PDF)

    Wednesday, May 13, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Abutters Meeting #2, May 13, 2026

  4. Document · PDF

    SBC Presentation 4/27/26 (PDF)

    Monday, April 27, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Building Committee Meeting, Apr 27, 2026

  5. Document · PDF

    Updated PSR Design Options (Shared on 4/27/26) (PDF)

    Monday, April 27, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Document for Building Committee Meeting, Apr 27, 2026

  6. Document · PDF

    SBC Presentation 5/20/26 (PDF)

    Wednesday, May 20, 2026

    Restriction Alternative) New Building Footprint Existing Building Footprint 9 Summary: • Addition/renovation (On the Existing Footprint, on the Parking Lot to the west and a portion of Edgerly Field to the north) which proposes

    Presentation slides for Building Committee Meeting, May 20, 2026

  7. Document · PDF

    Parking Memo & Plan (PDF)

    Tuesday, August 25, 2026

    Lord Project Number: 25100 From: Laura Swan Date: 8/25/2026 Project Name: Medford High School RE: Parking Program-DRAFT Distribution: This memorandum is intended to describe our best understanding of the existing parking utilized

    Document for Building Committee Meeting, Aug 25, 2026

  8. Document · PDF

    Evaluation of Existing Conditions (PDF)

    Thursday, June 25, 2026

    other site improvements vary significantly between the six PSR Alternatives; A.1, B.1.2, C2.2, C.3.4, D.1.1, and D.2.1. Parking options being considered include surface parking, construction of a 4-story parking garage, or field/stadium over below

  9. Document · PDF

    Final Evaluation of Alternatives (PDF)

    Thursday, June 25, 2026

    Building Location Existing Footprint Existing Footprint Existing Footprint & Fields Existing Footprint & Fields Existing Footprint & Fields Parking Lot & Existing Footprint Parking Lot & Existing Footprint Modulars Required

  10. Document · PDF

    SBC Presentation 2/11/26 (PDF)

    Wednesday, February 11, 2026

    subcontractor expenses (not CM expenses). For this PDP level estimate these categories are: Renovation, Addition/New Construction, Sitework, Parking, Pool Scope, Hazmat Removal and Demolition (See rows 1-10) Construction Cost The cost of construction which

    Presentation slides for Building Committee Meeting, Feb 11, 2026

  11. Document · PDF

    Building Committee Meeting, February 11, 2026 — pDP Comparative Cost Analysis (PDF)

    Wednesday, February 11, 2026

    subcontractor expenses (not CM expenses). For this PDP level estimate these categories are: Renovation, Addition/New, Sitework, Parking, Pool Scope, Hazmat Removal and Demolition (See rows 1-11) Construction Cost The cost of construction which Includes

    Document for Building Committee Meeting, Feb 11, 2026

  12. Document · PDF

    Building Committee Meeting, March 23, 2026 — six Design Options Chosen (PDF)

    Monday, March 23, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Document for Building Committee Meeting, Mar 23, 2026; Document for Community Forum #3, Apr 15, 2026

  13. Document · PDF

    Community Forum #3 4/15/26 (PDF)

    Wednesday, April 15, 2026

    Existing 4 Stories to remain • Estimated duration of 54 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Edgerly fields (2) renovated in place, two practice fields

    Presentation slides for Community Forum #3, Apr 15, 2026

  14. Document · PDF

    Final 6 PSR Design Options Presentation (PDF)

    Monday, June 1, 2026

    Educational Program • Existing 4 Stories to remain • Estimated duration of 60 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Maintains existing field inventory - Edgerly fields

    Meeting notes for Building Committee Meeting, Jun 1, 2026

  15. Document · PDF

    Community Forum #5 6/3/26 (PDF)

    Wednesday, June 3, 2026

    Educational Program • Existing 4 Stories to remain • Estimated duration of 60 months • 56 Modular Classrooms required • Parking : Existing parking lots to remain, renovated for accessibility compliance only • Fields : Maintains existing field inventory - Edgerly fields

    Presentation slides for Community Forum #5, Jun 3, 2026

  16. Document · PDF

    SBC Presentation 3/23/26 (PDF)

    Monday, March 23, 2026

    located so all students will access these spaces. So students do not feel singled out or 'special'. " • Parking congestion • Traffic flow • Bathroom privacy/safety • Pick-up/drop-off logistics. "Make a path for cars that goes completely

    Presentation slides for Building Committee Meeting, Mar 23, 2026

  17. Document · PDF

    2026 10 01 Sustanability & Systems AT Meeting 07 notes (PDF)

    Thursday, October 1, 2026

    Officer Sarah Michelman, Medford Resident, Sustainable Design Consultant at The Green Engineer Nicole Morell, SBC Member Jessica Parks, Medford Resident, MIT Energy Efficiency Project Manager Brenda Pike, City of Medford Climate Policy Planner Luke Preisner

    Minutes for Sustainability & MEP Systems Advisory Meeting, Oct 1, 2026

  18. Document · PDF

    SBC Presentation 6/10/26 (PDF)

    Wednesday, June 10, 2026

    folding into the high school project." D1.1 – ( 22) VOTES "D.1.1 NP — choosing this because I like the parking in the middle, making fields and building equally accessible, a new pool and gym ensure

    Presentation slides for Building Committee Meeting, Jun 10, 2026

  19. Document · PDF

    Site, Safety & Security Advisory Meeting, 2026-10-01: Presentation slides (PDF)

    Thursday, October 1, 2026

    Meeting #4 Agenda • Welcome & Introductions • Advisory Team Recommendation Development ❑ Parking Program ❑ Updated Site Layout ❑ Edgerly Track & Field ❑ Pedestrian Experience: ECC Breezeway ❑ Call for Assistance/ AED • Next Steps

    Presentation slides for Site, Safety & Security Advisory Meeting, Oct 1, 2026

  20. Document · PDF

    Evaluation Criteria Matrix (updated 3/19/26) (PDF)

    Thursday, March 19, 2026

    Addition Retain and Renovate Gym, Pool, and Wing E while constructing a New Addition on Parking Lot Retain and Renovate Gym, Pool and Wing E while constructing a New Addition in the center

    Document for Building Committee Meeting, Mar 17, 2026

  21. Document · PDF

    Evaluation Criteria Matrix (PDF)

    Thursday, March 19, 2026

    Addition Retain and Renovate Gym, Pool, and Wing E while constructing a New Addition on Parking Lot Retain and Renovate Gym, Pool and Wing E while constructing a New Addition in the center

    Document for Building Committee Meeting, Mar 17, 2026

  22. Document · PDF

    SBC Presentation 10/6/26 (PDF)

    Tuesday, October 6, 2026

    Approach VI. Review Project Adjacencies & Related Efficiencies for remaining project categories VII. Review Project Alternates for Parking & Athletic Fields VIII. Consider Previously Tabled Space Efficiency Proposals IX. Adjournment

    Presentation slides for Building Committee Meeting, Oct 6, 2026

  23. Document · PDF

    Community Forum #2, March 5, 2026 — community workshop follow-up input (March 16, 2026) (PDF)

    Thursday, March 5, 2026

    Architect Kate Tooke Landscape Architect SMMA Agency Matt Gulino Project Manager LeftField Berit Schurke Landscape Designer Rosemary Park Ed Planner Emily Ehlers HVAC Engineer Laura Swan Civil Engineer Jen Carlson Project Director Jamay Li Architectural

    Document for Community Forum #2, Mar 5, 2026

  24. Document · PDF

    Sustainability & MEP Systems Advisory Presentation 10/1/26 (PDF)

    Thursday, October 1, 2026

    Sustainability and MEP Systems – SD Preliminary Solar PV System Assessment Roof Solar Photovoltaic (PV) System Parking Solar Photovoltaic (PV) System Low Ballasted System High Canopy System Long Span Canopy System Parking Space Cover System Solar

    Presentation slides for Sustainability & MEP Systems Advisory Meeting, Oct 1, 2026

  25. Document · PDF

    Initial PDP Design Options (Voted by SBC on 3/23/26) (PDF)

    Monday, March 23, 2026

    project cost of $825,209,435 million. • Option B.2.1 : Addition/renovation (On the Existing Footprint and on the Parking Lot to the south) which proposes 186,280 sf of new construction as 3 Stories, in place

  26. Document · PDF

    Site, Safety & Security Advisory Meeting, 2026-10-01: Minutes (PDF)

    Thursday, October 1, 2026

    Civil Engineer Matt Rice, Principal-in-Charge, Architect Laura Swan, Civil Engineer Erik Vangsness, Landscape Architect Rosemary Park , Architect, Ed Planner Jamay Li, Architect Kate Tooke, Landscape Architect, Agency Kazia Rodrigo, Landscape Designer , Agency Berit

    Minutes for Site, Safety & Security Advisory Meeting, Oct 1, 2026

  27. Document · PDF

    Revised Pricing Matrix With Options C.2.2A & C.3.4A (PDF)

    Tuesday, June 9, 2026

    Sitework (base including all at-grade surface parking and fields

    Document for Building Committee Meeting, Jun 1, 2026

  28. Document · PDF

    2026.09.23 Sustainability & Systems Advisory Team Meeting #6 (PDF)

    Wednesday, September 23, 2026

    Officer Sarah Michelman, Medford Resident, Sustainable Design Consultant at The Green Engineer Nicole Morell, SBC Member Jessica Parks, Medford Resident, MIT Energy Efficiency Project Manager Brenda Pike, City of Medford Climate Policy Planner Luke Preisner

    Minutes for Sustainability & MEP Systems Advisory Meeting, Sep 23, 2026

  29. Document · PDF

    SBC Minutes 4/27/26 (PDF)

    Monday, April 27, 2026

    resolved that the next round of cost estimating will provide cost estimates breakdown as follows: ■ Parking: a) Base estimate will include surface grade parking and note the number of allowable spaces and note

    Minutes for Building Committee Meeting, Apr 27, 2026

  30. Document · PDF

    SBC Agenda 4/27/26 (PDF)

    Monday, April 27, 2026

    resolved that the next round of cost estimating will provide cost estimates breakdown as follows: 1. Parking: a) Base estimate will include surface grade parking and note the number of allowable spaces and note

    Agenda for Building Committee Meeting, Apr 27, 2026

  31. Document · PDF

    SBC Presentation 8/25/26 (PDF)

    Tuesday, August 25, 2026

    panels) $2,683,800 $3,274,236 PV2 - Provide Canopy Structures only for PV Panels over Parking, Drive Aisles and CTE Yards for NetZero (assume PPA for all PV Panels

    Presentation slides for Building Committee Meeting, Aug 25, 2026

  32. Document · PDF

    PSR Alternates (PDF)

    Friday, July 17, 2026

    owns the panels) 2,683,800 $ 3,274,236 $ PV2 - Purchase Additional Canopy Mounted PV Panels over Parking, Drive Aisles and CTE Yards for NetZero (assume City/District owns the panels

  33. Document · PDF

    SBC Presentation 12/22/25 (PDF)

    Monday, December 22, 2025

    Accessibility Exterior - Majority of accessible parking spaces have slope issues and/or non-compliant signage - Accessible routes have several issues of non- compliance - Several stairs lack compliant handrails - Majority of public entrances have barriers: • Some have

    Presentation slides for Building Committee Meeting – Design Team Update, Dec 22, 2025

  34. Document · PDF

    Sustainability & MEP Systems Avisory Presentation 9/23/26 (PDF)

    Wednesday, September 23, 2026

    Baseline) - - - $77,290,000 $173,009,000 Option 1 Ground Source Heat Pump - GSHP 9 acres Main Parking Lower Field Areas Temporary HVAC System – 3.5 yrs $93,417,000 $164,744,000 Option 2 Hybrid

    Presentation slides for Sustainability & MEP Systems Advisory Meeting, Sep 23, 2026

  35. Document · PDF

    Design Alternatives (Slide 14 – Updated 3.19.26) (PDF)

    Thursday, March 19, 2026

    Alternatives for High Level Cost Estimating / Rules of Thumb – Landscape options: color key – Parking is consistent at 425 spaces for all options in different configurations. Preschool Play space and CTE yards are consistent

    Document for Building Committee Meeting, Mar 17, 2026

  36. Document · PDF

    SBC Presentation 1/14/26 (PDF)

    Wednesday, January 14, 2026

    Alternatives for High Level Cost Estimating / Rules of Thumb – Landscape options: color key – Parking is consistent at 425 spaces for all options in different configurations. Preschool Play space and CTE yards are consistent

    Presentation slides for Building Committee Meeting, Jan 14, 2026

  37. Document · PDF

    Site Safety & Security Advisory Group Notes 3/11/26 (PDF)

    Wednesday, March 11, 2026

    High School Project Number: 25100 RE: Advisory Team - Site, Safety & Security Meeting Date: 03/11/2026 Prepared by: Rosemary Park Meeting Number: 3 Distribution: Attendees Owner SMMA & Consultants Leftfield Nicole Branley, Resident Chief Jack Buckley, Chief

    Meeting notes for Site & Security Advisory Meeting, Mar 11, 2026

  38. Document · PDF

    District Response to PDP Comments (PDF)

    Tuesday, May 19, 2026

    MACRIS shows portions of several parcels, including Medford High School, Temple Shalom of Medford, Victory Park, and the City-owned parcel at 0 Ronaele Rd as part of the Middlesex Fells Inventory Area. Inventory Areas

    Document for Building Committee Meeting, May 20, 2026

  39. Document · PDF

    SBC Minutes 8/25/26 (PDF)

    Tuesday, August 25, 2026

    estimated total project cost of $768,577,410. VII. Determine Baseline Size for Auditorium VIII. Design Updates & Parking Program The project team did a study on parking on the current site, which comes

    Minutes for Building Committee Meeting, Aug 25, 2026

  40. Document · PDF

    Appendices (PDF)

    Thursday, June 25, 2026

    MACRIS shows portions of several parcels, including Medford High School, Temple Shalom of Medford, Victory Park, and the City-owned parcel at 0 Ronaele Rd as part of the Middlesex Fells Inventory Area. Inventory Areas

  41. Document · PDF

    SMMA Designer Submission (PDF)

    Wednesday, August 27, 2025

    core of our process. The educational programming team brings the combined expertise of SMMA’s Rosemary Park (planning), New Vista Design’s David Stephen (visioning), and Dr. Karen Maguire (CTE leadership). Sustainable design thinking will

  42. Document · PDF

    SBC Presentation 2/23/26 (PDF)

    Monday, February 23, 2026

    fixed % of Roof Surface Incl in base bid $0 PV2 Purchase Additional Canopy Mounted PV Panels over Parking & Roadways $32,619,060 $32,619,060 PV3 Canopy Structure only for PV Panels over Parking & Roadways

    Presentation slides for Building Committee Meeting, Feb 23, 2026

  43. Document · PDF

    PDP Comments from the MSBA (PDF)

    Tuesday, May 5, 2026

    District’s PSR submittal, please provide the following: • A description of how the number of parking spaces for staff and visitors will be determined, i.e., based on daily school needs, after-hours athletic/performance needs, and/or

    Document for Building Committee Meeting, May 20, 2026

  44. Document · PDF

    SBC Presentation 6/18/26 (PDF)

    Thursday, June 18, 2026

    that are not specifically related to program space. This includes the different pool options (POOL), field over parking options (PARK), access roads (ACCESS), PV options (PV), mechanical systems (HVAC), mass timber options (TIMB), and phasing

    Presentation slides for Building Committee Meeting, Jun 18, 2026

  45. Document · PDF

    SBC Minutes 8/11/25 (PDF)

    Monday, August 11, 2025

    Site Selection Matrix A. Site Options Discussion and Potential Vote: Possible removal of Medford Square and Columbus Park as options; only the Medford High property to remain for the Feasibility Study LeftField showed a chart

    Minutes for Building Committee Meeting – DSP, Aug 11, 2025

  46. Document · PDF

    Site Safety & Security Advisory Group Minutes 12/18/25 (PDF)

    Thursday, December 18, 2025

    Security AT: - Reviews development of the site design for traffic, circulation, safety and security. Includes conversations about parking, driveways and circulation, fields, and offsite improvements and coordination with City Departments. Overall process: 4 meetings Listen

    Minutes for Site & Security Advisory Meeting, Dec 18, 2025

  47. Document · PDF

    Educational Profile (PDF)

    Sunday, June 30, 2024

    space-constrained and likely has only a few viable options for consideration, including Medford Square and Columbus Park

  48. Document · PDF

    Community Forum #6: Eco-Charrette (PDF)

    Thursday, September 17, 2026

    Medford High School Eco-Charrette – SD Preliminary Solar PV Assessment Roof Solar Photovoltaic (PV) System Parking Solar Photovoltaic (PV) System Low Ballasted System High Canopy System Long Span Canopy System Parking Space Cover System Solar

    Presentation slides for Community Meeting #6 – Eco-Charrette, Sep 17, 2026

  49. Document · PDF

    Sustainability & MEP Systems Advisory Group Presentation 1/15/26 (PDF)

    Thursday, January 15, 2026

    Chris Hogan 7. Elisabeth Krautscheid 8. Ken Lord 9. Sarah Michelman 10. Nicole Morell 11. Jessica Parks 12. Brenda Pike 13. Luke Preisner 14. Chris Richard 15. Paul Ruseau 16. Nathan Scott Sustainability

    Presentation slides for Sustainability & MEP Systems Advisory Meeting, Jan 15, 2026

  50. Document · PDF

    Site Safety & Security Advisory Group Minutes 1/13/26 (PDF)

    Tuesday, January 13, 2026

    formal entrance to the Fells – very concerned about safety. However, because people can park at MHS, it is used in that way. Mobility and Access Kate Tooke reviewed metrics on modes of transportation

    Minutes for Site & Security Advisory Meeting, Jan 13, 2026

  51. Document · PDF

    Site & Security Advisory Meeting, March 11, 2026 — security Recommendations (PDF)

    Wednesday, March 11, 2026

    Saturday circulation and parking are major issues. ⚫ Improving on-site circulation will benefit Saturday traffic as well 19 Site circulation is confusing; need modern flow. ⚫ 20 Public transit limited; need more MBTA buses. ⚫ Meeting with

    Document for Site & Security Advisory Meeting, Mar 11, 2026

  52. Document · PDF

    Site Safety & Security Advisory Group Presentation 1/13/26 (PDF)

    Tuesday, January 13, 2026

    friendly design. Reviews development of the site design for traffic, circulation, safety and security. Includes conversations about parking, driveways and circulation, fields, and offsite improvements and coordination with City Departments. Reviews exterior design concepts including

    Presentation slides for Site & Security Advisory Meeting, Jan 13, 2026

  53. Document · PDF

    Community Forum #1 1/7/26 (PDF)

    Wednesday, January 7, 2026

    Designer / SMMA Matt Rice Principal-in-Charge Helen Fantini Project Manager Rosemary Park Educational Planner: Programming SMMA is leading the design and educational planning services for the new Medford High School. Michael Pardek Architect Erin

    Presentation slides for Community Forum #1, Jan 7, 2026

  54. Document · PDF

    2.9.26 MHS Space Summary Overview Draft (PDF)

    Monday, February 9, 2026

    Page 01 Memorandum To: MCHS School Building Committee Project Number: 25100 From: Rosemary Park Date: 02/09/26 Project Name: Medford High School RE: Preliminary Design Program (PDP) Initial Program Summary of Spaces Distribution: MCHS School Building

    Meeting notes for Building Committee Meeting, Feb 11, 2026

  55. Document · PDF

    Building Committee Meeting, January 14, 2026 — minutes (PDF)

    Wednesday, January 14, 2026

    building to support the programming needs. These options include phased renovation ideas and building into existing parking lots or spaces that are on the site. Other options include building up on the existing building, compacting

    Minutes for Building Committee Meeting, Jan 14, 2026

  56. Document · PDF

    Sustainability & MEP Systems Advisory Group Minutes 1/15/26 (PDF)

    Thursday, January 15, 2026

    Officer Sarah Michelman, Medford Resident, Sustainable Design Consultant at The Green Engineer Nicole Morell, SBC Member Jessica Parks, Medford Resident, MIT Energy Efficiency Project Manager Brenda Pike, City of Medford Climate Policy Planner Luke Preisner

    Minutes for Sustainability & MEP Systems Advisory Meeting, Jan 15, 2026

  57. Document · PDF

    Document A PSR Comments from MSBA (PDF)

    October 2026

    each prospective site including: a) Natural site limitations ☒ ☐ ☐ ☐ b) Building footprint(s) ☒ ☐ ☐ ☐ c) Athletic fields ☒ ☐ ☐ ☐ d) Parking areas and drives ☒ ☐ ☐ ☐ e) Bus and parent drop-off areas ☒ ☐ ☐ ☐ f) Site access and surrounding site features

  58. Document · PDF

    SBC Presentation 5/12/25 (PDF)

    Monday, May 12, 2025

    Text Description automatically generated with medium confidence ▪ Conservation Commission ▪ Park Commission ▪ Arts Collaborative Medford ▪ Medford Boat Club ▪ Condon Shell ▪ Medford Kiwanis ▪ PTO Meetings ▪ Farmers Market ▪ Council On Aging/Senior Housing ▪ School Committee ▪ City Council ▪ Board

    Presentation slides for Building Committee Meeting – Team Introduction, May 12, 2025

  59. Document · PDF

    2026 11 02 Site Safety Security Advisory Team Meeting 5 Minutes (PDF)

    Monday, November 2, 2026

    Principal-in-Charge, Architect Laura Swan, Civil Engineer Erik Vangsness, Landscape Architect Ethan Fleig Landscape Designer Rosemary Park , Architect, Ed Planner Jamay Li, Architect Kate Tooke, Landscape Architect, Matt Allain, Security Consultant , Good Harbor Techmark

    Minutes for Site, Safety & Security Advisory Meeting, Nov 2, 2026

  60. Document · PDF

    SBC Minutes 5/20/26 (PDF)

    Wednesday, May 20, 2026

    Modulars 1000 ft. 52 modulars in option A where do they go? (Matt Rice: 2 stories, on parking lot. ) Andrew: put the modulars on a deck and park underneath ○ A and B are the greenest